Project Information

Engineering


The Engineering and Construction Departments are responsible for the design, planning and construction of City-initiated public development projects, and the review and inspection of all privately installed improvements. They are also responsible for the operation and maintenance of traffic signals. 

Maintenance of the City's infrastructure at various locations within the city is performed annually. A list of projects performed on an annual basis may include the following: 
  • Concrete Repair 
  • Catch Basin Repair 
  • Street Striping 
  • Preventative Maintenance 
  • Guardrail Repair 
  • Asphalt Repair 
  • Manhole Repair 
  • Materials Testing 
  • Sewer Grouting 
  • Emergency and Miscellaneous Roadway Repair 
  • Sanitary and Storm System Repair 

In addition to annual programs, the City Engineer plans and develops projects for continued maintenance and upgrade of the City’s infrastructure. These projects tend to focus on specific issues that become apparent and can be rectified through repair or upgrade of the current system. 


Bainbridge Road Tree Planting Project

 

Contractor: Vizmeg

 


  • Limits: Bainbridge Road from SOM Center Road, the east corporate line
  • Scope: Planting of new trees and water for 20 weeks
  • Update: Tree planting has been completed, watering is ongoing.

Tennis Court Renovation Project


Contractor: Chagrin Valley Paving



  • Limits: Tennis Courts at the Community Center
  • Scope: Renovation of the tennis courts including fencing and pathway
  • Start: October 30, 2017
  • End: Expect to be substantially complete in July
  • Update: The contractor has resumed work this May to complete the painting, striping and fencing in the first phase before beginning work in the second phase.

SOM Center Retaining Wall Refacing and Fence Replacement Project


Contractor: Sander Contracting



  • Limits: SOM Center Road on both sides between Bainbridge Road and Aurora Road
  • Scope: The project includes the aesthetic re-facing of retaining walls with thin brick veneer as well as the rehabilitation of the drainage system, installation of decorative fencing and separate sidewalk and curb replacement on the north end of the retaining walls on SR 91.
  • Start: May 23, 2018
  • Substantial Completion Date: August 31, 2018
  • Update: The contractor has begun work on the east side of SOM Center using day zones to restrict northbound traffic between the hours of 9 AM and 3 PM, reopening the curb lane at the end of each day. The sidewalk on the east side is closed.

Annual Concrete Repair Program


Contractor: Tri Mor Corporation


  • Limits: Various locations listed below and tentative schedule
  • Scope: Construction of concrete pavements or sections of, including the roadways, sidewalks; curbs; drive aprons; and handicap ramps
  • Start: April 25, 2018
  • Substantial Completion Date: October 30, 2018
  • Update: Contractor has completed one side of work on Ramblewood Court and Shadowbrook Drive and has begun the removal on the opposite side.
The following list of areas that have been identified for concrete pavement repair or replacement under the 2018 Annual Concrete Repair Program: 
  • Naiman Parkway - Concrete pavement will be replaced full width from 5250 south to 5260. 
  • Shadowbrook Drive -
  • Ramblewood Court - Multiple major concrete pavement repairs will be made as necessary.
  • Lansdowne Drive - Concrete pavement will be replaced in its entirety.
  • Stony Brook Lane - Will be replaced full width from 32530 tp 32570
  • Tandem Court - From Coachman north including removal of the cul-de-sac
  • North Oval - Concrete pavement will be replaced full width from the new pavement at the Fox Run intersection to 5861.
  • Coachman Lane - Full width concrete pavement will be replaced from 33160 to 33635 and the Hansom Lane intersection.
  • Outley Park Drive - Will be replaced full width from Fox Hill Drive through the Warwickshire east intersection tot he newer pavement at the cul-de-sac
  • North Roundhead - Full width pavement will be replaced from 31826 South Roundhead northerly to 32275 North Roundhead.
A brochure for information regarding construction of the project is available.

CONCRETE STREET REPAIR TENTATIVE SCHEDULE

All schedule timing is weather dependent.
STREET START COMPLETE
Naiman Parkway May 9 June 6
Shadowbrook Drive May 11 June 4
Ramblewood Court May 17 June 4
Lansdowne Drive June 1 July 12
Stony Brook Lane June 6 July 3
Tandem Court July 2 July 27
North Oval July 23 August 17
Coachman Lane July 30 September 7
Outley Park August 27 October 5
Roundhead Drive September 10 October 18