Project Information

Engineering


The Engineering and Construction Departments are responsible for the design, planning and construction of City-initiated public development projects, and the review and inspection of all privately installed improvements. They are also responsible for the operation and maintenance of traffic signals. 

Maintenance of the City's infrastructure at various locations within the city is performed annually. A list of projects performed on an annual basis may include the following: 
  • Concrete Repair 
  • Catch Basin Repair 
  • Street Striping 
  • Preventative Maintenance 
  • Guardrail Repair 
  • Asphalt Repair 
  • Manhole Repair 
  • Materials Testing 
  • Sewer Grouting 
  • Emergency and Miscellaneous Roadway Repair 
  • Sanitary and Storm System Repair 

In addition to annual programs, the City Engineer plans and develops projects for continued maintenance and upgrade of the City’s infrastructure. These projects tend to focus on specific issues that become apparent and can be rectified through repair or upgrade of the current system. 


Cochran Road Reconstruction Phase II

 

Contractor: Tri Mor Corporation

The contractor is scheduled to return the end of April to complete the replacement of a few sidewalks followed by restoration work along Cochran Road from Solon Industrial Parkway south to the City limits. Work will be complete in day zones.

2017 Annual Asphalt Repair Program

 

Contractor: Ronyak Paving

The contractor has begun work at Grantwood Clubhouse, widening the front asphalt entrance with additional drainage. The concrete curb and sidewalk will be replaced and four small planters removed. Work is expected to be completed in May.

Tennis Court Renovation Project

   
Contractor: Chagrin Valley Paving

The contractor is scheduled to start back the end of April to complete the painting, striping and fencing in the first phase before beginning work in the second phase.

This project is expected to be substantially complete by June.

Bainbridge Road Culvert Project

    
Contractor: Trax Construction

The contractor has completed the east and west walls and is now working on the ceiling of the culvert repair. The project is scheduled to be substantially complete by spring 2018.

Bainbridge Road Tree Planting Project

     
Contractor: Vizmeg Landscape

The project entails the planting of new trees along Bainbridge Road from SOM Center Road, to the east corporate line. After the trees are planted the contractor will water the trees for 20 weeks, by filling the watering bag installed at each location. The planting is expected to be completed by the end of  April.

Bainbridge Road Culvert Project

     
Contractor: Trax Construction

The contractor has completed the east and west walls and is now working on the ceiling of the culvert repair. The project is scheduled to be substantially complete by spring 2018.

Bainbridge Road Culvert Project

     
Contractor: Trax Construction

The contractor has completed the east and west walls and is now working on the ceiling of the culvert repair. The project is scheduled to be substantially complete by spring 2018.

SOM Center Retaining Wall Refacing and Fence Replacement Project


Contractor: Sander Contracting

The project includes the aesthetic refacing of retaining walls with thin brick veneer on both sides of SOM Center Road between Bainbridge Road and Aurora Road, as well as the rehabilitation of the drainage system and installation of decorative fencing at the top of the walls.

Annual Concrete Repair Program

      
Contractor: Tri Mor Corporation

The following list of areas that have been identified for concrete pavement repair or replacement under the 2018 Annual Concrete Repair Program:
  • North Roundhead - Full width pavement will be replaced from 31826 South Roundhead northerly to 32275 North Roundhead.
  • Coachman Lane - Full width concrete pavement will be replaced from 33160 to 33635 and the Hansom Lane intersection.
  • Tandem Court - From Coachman north including removal of the cul-de-sac
  • Outley Park Drive - Will be replaced full width from Fox Hill Drive through the Warwickshire east intersection tot he newer pavement at the cul-de-sac
  • Ramblewood Court - Multiple major concrete pavement repairs will be made as necessary.
  • Stony Brook Lane - will be replaced full width from 32530 to 32570
  • Lansdowne Drive - Concrete pavement will be replaced in its entirety.
  • North Oval - Concrete pavement will be replaced full width from the new pavement at the Fox Run intersection to 5861.
  • Naiman Parkway - Concrete pavement will be replaced full width from 5250 south to 5260.
  • Arthur Road Pool - The remaining concrete pool decking will be replaced.