City of Solon
Building Department
34200 Bainbridge Road
Solon, Ohio 44139
    
Phone: 440.349.6737
Fax: 440.349.6322
 

Building Department

Commercial Permits

CITY OF SOLON BUILDING PERMIT PROCEDURES
(Non-residential Projects)

To obtain a building permit the following procedures must be followed:

A.     CHANGES REQUIRING A PERMIT

B.     INFORMATION REQUIRED UPON SUBMISSION

Building Department: (440) 349-6737

  1. Submit four sets of detailed drawings with the following information to the Building Department:
    • Embossed with architect’s and/or engineer’s original signature over the stamp
    • A completed building permit application:
      • List the general contractor and all subcontractors
      • The Use Group and Class of the building, from the OBC (Ohio Building Code)
      • Signature and phone number of qualified representative
    • Disclose use or storage of hazardous, flammable or combustible materials  
  2. Submit four sets of plans showing the following information to the Building Department: underground fire main, yard hydrant location, sprinkler system, alarm system, and fixed fire suppression if applicable.
  3. Submit two sets of site plans to the Building Department, including:
    • Site utilities, grading plan, erosion control drawings (typical details for site work)
    • Calculations for storm sewers and detention basin

C.     PLAN EXAMINATION

  1. Two sets of the drawings will be forwarded to the plans examiner (via the Building Department) for review
  2. The plans examiner will submit a letter of recommendation that addresses the following:  
    • All code requirements which have not been addressed on the original drawings
    • Drawings reviewed per the Ohio Building Code
  3. One set of the drawings will be forwarded to the Fire Department (via the Building Department) for review of OBC and Ohio Fire Code.  Applicant will receive report. 

D.     APPLICANT’S RESPONSIBILITY

  1. The representative receives a copy of the letter and must address the items in any of the following manners:
    • By submitting a letter of compliance to the attention of the Building Commissioner addressing the code violations 
    • By submitting 3 sets of revised drawings

E.      CONSTRUCTION PROCEDURES

  1. An approved set of drawings shall remain on the site at all times
  2. All inspection requests for inspection should be requested 24 hours in advance by calling the Building Department at (440) 349-6737
  3. A final inspection is required so a Certificate of Occupancy can be issued and the project considered complete

Special Note:  Contractors shall be listed on the permit application and must be registered with our Building Department before a permit can be issued.

Please contact the Building Department at (440) 349-6737 for further information.

 

 

City Council | Council Agenda | Council Committees | Boards and Commissions | Ordinances | Office of the Mayor
Arts | Finance | Fire | Grantwood | Human Resources | Planning & Development | Police | Public Works | Recreation | Senior Services
City Calendar | Recreation Brochure | Senior Services Calendar
Government Offices | Frequently Requested Phone Numbers | Other Links
Driving Directions to Solon City Hall | Contact Solon
subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link
subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link