Aurora Road Infrastructure Project - Phase 1 Update 11/3/23

79d54ff7-08ef-4710-feb2-d90da3fe7f33


19303f27-095a-d1e4-4d3c-bb4b7b6b3b74

Work Completed This Week

Tri Mor has installed new 12” watermain and fire hydrants on the south side of Aurora Road from 35775 Aurora Road to approximately 36050 Aurora Road.. 



79d54ff7-08ef-4710-feb2-d90da3fe7f332-Week Look Ahead

During the next two weeks Tri Mor will continue to install new 12” watermain and fire hydrants from 36050 Aurora Road to approximately 60 feet west of the Liberty Road intersection.  Two crews will then drop back and install remaining fire hydrants and extend waterlines to the various adjacent streets that will be eventually connected to the new water main.  Once this is completed, the new water main will be filled and pressure tested.  Once pressure testing is successfully completed, then Cleveland Water will Chlorinate the new water main.