Aurora Road Infrastructure Project - Phase 1 Update 11/20/23

0c7d6fa7-e9f3-1bbf-00dc-e1045a0e6898


0c7d6fa7-e9f3-1bbf-00dc-e1045a0e6898

Work Completed This Week

This week Tri Mor successfully passed a pressure test of the new 12” water main from the west end of the project to Liberty Road. The Cleveland Water Department has begun the process of chlorinating the new water main.  Tri Mor began installing new storm sewer laterals from the south side of Aurora Road to the centerline where they will be picked up later to complete the laterals across the road.  They have also been extending sanitary lateral cleanouts back to the right-of-way on the south side. 



bf0ad1fc-ca8f-7f5d-f41f-954bb4afddba2-Week Look Ahead

During the next two weeks Tri Mor will continue extending sanitary lateral cleanouts to the right-of-way on the south side.  They will also install new proposed sanitary laterals where required.  Once the chlorination is completed Tri Mor will begin installing new water services to each property from the west end on the project to Liberty Road and connecting them to the new water main.  This process will require brief scheduled water service shutoffs at each building for which you will be notified.



d0b190b3-14c1-8d23-8255-abd284b6ccd7

Leaf Collection:  Leaf collection in the Aurora Road Construction zone will continue to occur every Sunday morning.

Trash Collection:  Please be sure to have your trash & recycle cans out by 7:00 am so that Tri Mor can efficiently take them across the street for pickup.