Work Completed This Week

Tri Mor has completed extending sanitary sewer laterals and cleanouts to the right-of-way on the south side of Aurora Road from the west end of the project to Liberty Road.  The new water main from the west end of the project to Liberty  Road has passed.



66d9a92f-e162-411d-96e3-dd1b3ebd5bc52-Week Look Ahead

During the next two weeks Tri Mor crews will begin installing new water services from the new water main to the right-of-way a teach building from the west end of the project toward Liberty Road and connecting the buildings to the new water main. The process will require a brief (approximately ½ hour) shut down of water at each building as it is connected. Tri Mor will knock on the door of each building as the connection time approaches to verify a good time for the transition.



08c4e168-7ea8-6247-5e34-69b6a1a708c4

Leaf Collection in the Aurora Road Construction Zone will continue to occur every Sunday morning.



The week of December 18th, the one-way eastbound zone on Aurora Road will be extended east past Liberty Road and Andre Lane. Northbound and Southbound.2e48b1a5-07ea-0c8f-6332-58a7e620b867